Anjali - AUT - Weekly Status Report for Week 1 (26 May 2015)

What have you accomplished this week (list specific items accomplished)?
  • Had a hangout session with the mentor to discuss project approach.
  • Completed the environment set up and checked if its working fine by writing login test for Systers-wiki.
  • Initial requirements collection from MeetUp team.
  • Made local work repo in Github . Here is the link.
  • Revised the timeline according to the data collected from the meetup team. It has been added to the my wiki page.
  • Tried running portal on localhost but getting some error.

What issues or roadblocks have you encountered this week?
  • There was some problem with my firefox browser because of my proxy settings and none of the tests were running.
  • Getting error while running portal.

Have they been resolved, and if so, how?
  • Yes, the firefox issue has been resolved. The tests are running fine.
  • For portal, the issue has not been resolved, still working on it.


Do any of the issues or roadblocks still exist and what steps have been taken to resolve them?
  • Yes, portal is not running on local machine but I am working on it.

Is further assistance necessary to resolve existing issues?
  • Yes if I am unable to do it.

What do you plan to accomplish next week?
  • For the next week I plan to create a list of generic tests according to the data collected from the dev team.
  • Try automating login test written through maven/ant.
  • Deploy portal on localhost to start with portal baseline testing to get ready till the first feature of meetup is implemented by dev team.

How does your progress compare to your project schedule?
  • My progress is going in line with my schedule.