Anjali - AUT - Weekly Status Report for Week 8 (13 July 2015)
What have you accomplished this week (list specific items accomplished)?
- Added test suites to Portal which are here https://github.com/Anjali05/MyWork_Gsoc/tree/master/SystersPortal/PortalTests/TestSuites .
- Added test results to the documentation.
- Tried Continuous Integration with Jenkins.
- Created test classes for meetup based on the mockups.
What issues or roadblocks have you encountered this week?
- N/A
Have they been resolved, and if so, how?
- N/A
Do any of the issues or roadblocks still exist and what steps have been taken to resolve them?
- N/A
Is further assistance necessary to resolve existing issues?
- N/A
What do you plan to accomplish next week?
- Implement meetup tests if the UI is ready.
- Refactor code.
- Update documentation
How does your progress compare to your project schedule?
- Behind.